[Dev] Cynara & Security-Manager - task schedule for next months

Tomasz Swierczek t.swierczek at samsung.com
Thu Oct 16 14:45:59 GMT 2014


Hi All,

 

Since our work on Cynara and Security-Manager becomes more and more
important to other platform components, we've decided to publish our
schedule for most important tasks here. Below you'll find dates when we
*plan* to have each of the items complete. These tasks match also work we do
together with Intel Security Team to ensure Crosswalk & launchers are
properly secured (Crosswalk integration is done in cooperation with all
interested parties, including Intel & Samsung WRT/Crosswalk guys).

 

 


Cynara: Client Library

 From

To 


Asynchronous API tests

2014-10-24

2014-11-07


Credential helpers configuration with tests

2014-09-01

2014-10-24


Client configuration API (cache size, timeouts)

2014-11-21

2014-12-05


 

 

 


Cynara: Admin Library

 

 


Listing and erasing sets of policies (implementation)

2014-11-14

2014-11-21


Tests for new commands

2014-11-21

2014-11-28


Offline mode

2014-09-01

2014-10-31


Offline command-line tool

2014-11-14

2014-11-28


Offline mode tests

2014-10-31

2014-11-21


 

 

 


Cynara: Service Daemon

 

 


Emergency mode (if we detect policy's DB is corrupted)

2014-10-24

2014-10-31


Database checksum

2014-10-17

2014-10-24


 

 

 


Cynara: Policy extensions

 

 


Plugins API implementation

2014-09-26

2014-11-14


Agent API implementation

2014-09-26

2014-10-24


"Ask User" plugin implementation

2014-11-14

2014-11-21


Sample agent for UI popups (using existing UI framework)

2014-10-24

2014-11-14


 

 

 


Cynara: Xwalk integration

 

 


Review of cynara usage

2014-10-10

2014-10-24


 

 

 


Cynara: DBus integration

 

 


usage of Cynara code in dbus

2014-09-26

2014-10-31


tests

2014-11-14

2014-11-28


supervision of services configuration

2014-10-31

INF


 

 

 


Cynara: System service security analysis

 

 


service/IPC/privileges analysis

2014-10-31

2014-11-21


supervision of JIRA tasks for Cynara usage

2014-11-07

INF


 

 

 


Security Manager: Application support

		

Discuss & agree on application directories structure for Crosswalk

2014-10-20

2014-10-24


Decide private data location for globally installed apps

2014-10-20

2014-10-24


Implement file (Smack) labeling in home folder of the user

2014-10-27

2014-11-07


Implement setting capabilities for launchers

2014-10-06

2014-10-24


Setup Cynara policy for non-application user processes

2014-10-20

2014-10-21


Label applications by appId, not pkgId

2014-10-20

2014-10-21


Integrate security-manager with Crosswalk

2014-10-01

2014-11-07


Using separate labels for applications

2014-11-03

2014-11-28


Refine Smack rules for applications (based on any possible problems/errors)

2014-11-03

2014-11-28


Provide API for amd to get appID from running apps

2014-10-20

2014-10-31


Separate repository for security-manager policy (groups per privilege)

2014-10-01

2014-10-14

			

Security Manager: User Support

		

Decide how to integrate gumd and security-manager

2014-10-13

2014-10-24


Design user profile mapping to privileges and allowed apps

2014-10-20

2014-10-31


Restructure Cynara policy setup to use policy buckets

2014-10-20

2014-10-24


Handle user creation and removal

2014-11-03

2014-11-21


Provide API for fine-tuning allowed applications for users

2014-11-24

2014-12-12


Provide API for fine-tuning privileges for users

2014-11-24

2014-12-12


Provide API for per-user privilege limiting ("privacy-manager")

2014-11-24

2014-12-12

			

Security Manager: Offline-mode Support

		

Support application registration during image build

2014-10-06

2014-10-24


Support proper user registration during image build

2014-11-24

2014-11-28

 

 

Best Regards,

 

cid:44YDXKW4QKNM at namo.co.kr

 

Tomasz Świerczek

Samsung R&D Institute Poland

Samsung Electronics

Office +48 22 377 95 59

Cell +48 503 135 021

 <mailto:t.swierczek at samsung.com> t.swierczek at samsung.com

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.tizen.org/pipermail/dev/attachments/20141016/764ff5f6/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 2228 bytes
Desc: not available
URL: <http://lists.tizen.org/pipermail/dev/attachments/20141016/764ff5f6/attachment-0001.png>


More information about the Dev mailing list